Tuesday 19 September 2017


‘St Peter’s: A Unique Forest Church’ Project
Project Update September 2017


Status
Last Month
This Month
Progress Against Plan
Green
Green
Match Funding
Green
Green
Project Costs
Green
Green


Hi all, it’s time for a quick project update again and I am happy to report that all is well with the project and its progress.


Over the last month, the project board have undertaken a day’s study trip to look at other projects including churches with cafes and spaces to let. This has been very informative and has helped us to understand how St Peter’s may operate. We also held a 3-day event on the 1-3rd September to gain information from people who pass by in the forest who are not regular church users. Part of this event included the temporary cloth wall being put in place for a week to simulate how the church may be configured in the future. Thank you to all of you who helped volunteer to make this happen. The event, although not overwhelmingly attended has provided us with lots of views and concerns which we will consider in shaping the churches future.

If you have any questions I can be contacted by e-mail at Peter@culturalengine.org.uk or 07527 329793,  Peter Vadden

No comments: